Illustration 7: Status of civil works macroblock N42 - Lean concrete base and pavements On the other hand, the completion of the construction of the slot raise corresponding to macroblock S04 was finalized, a milestone that marks a significant advance in its development. With the completion of these tasks, the mining preparation stage in this macroblock is considered finished, which represents a key step for its future incorporation into the productive phase. Once this stage was completed, efforts have focused on the execution of the ore pass, which are essential for the efficient handling of ore from the production level to the lower hauling levels. These systems include both the dumping points and the construction of chutes, elements that allow the flow of material and optimize the loading and transportation process.