Track 6: Mining Engineering and Mine Planning

Illustration 8: Status of civil works macroblock S04 In the central panel, mining preparation activities have continued to develop, mainly focused on the execution of civil works. Among the tasks carried out, the construction of containment walls, the enabling of draw points, the rock bolt of crossing, as well as the execution of pavements and lean concrete base, stand out, as can be seen in illustrations 9 and 10. The execution of slot raise was recently initiated, which constitutes a significant milestone within the preparation process. As a result of the sustained progress of these activities, a 99% completion rate is currently achieved in the civil works of the panel central, which shows a high degree of development and proximity to the completion of this stage. This level of progress allows for a more certain projection of the start of the subsequent phases, aimed at the commissioning of the operational systems and the incorporation of the panel into production.